Location: Borgen Blvd & Peacock Hill Gig Harbor, WA
Start Date: August 2015
Contract: $3.2 Million
Description: Earthwork and Utilities for the new construction of a continuing care retirement community that includes 186 Independent Living Units (ILU), 10 Cottages/Villas, a Clubhouse and underground parking garage on a 17.97 acre site.

Heron's Key Site

Additional Photos

 

Location: PUYALLUP RIVER AT FENNEL CREEK
Start Date: JULY 2015
Contract: $ 500,000
Description: CONSTRUCTION OF SIDE CHANNELS AND 60+ log structures AlONG FENNEL CREEK HABITAT.   INCLUDING FEATURES like COFFERDAMS AND DE-WATERING

 

Location: Lacey
Start Date: May 2015
Contract: $1.5 Million
Description: ACI provided construction of a modern roundabout.  The scope of the work included; storm water, water, sewer, flashing beacons, illumination, landscaping and other work.

 

Location: PUYALLUP RIVER NORTH OF ORTING
Start Date: JULY 2015
Contract:$ 350,000
Description:CONSTRUCTION OF TWO IN-WATER ENGINEERED LOG JAMS (ELJ’S) INCLUDING PRECAST DOLO’S, COFFERDAMS, DEWATERING AND TEMPORARY BRIDGE.