Location: : fife, WA
Start/finish Date: may 2018 – june 2018
Contract: $1,161,982.83
Description: This Contract provides for the improvement of the existing culverts at 54th Avenue East and 8th Street East by replacing the existing twin 68-inch culverts with a box culvert, including reconstruction of 54th Avenue East and 8th Street East in the vicinity of the culvert crossing, including utility coordination, and the replacement of the culverts in the vicinity of 54th Avenue 50 East and 4th Street East and other work.
Culvert was finished in one 3 day closure.

 
 

Location: gig harbor, wa
Start/finish Date: april 2018 - july 2019
Contract: $7 million
Description: RESIDENTIAL SITE DEVELOPMENT OF 174 loTS - clearing, tesc, earthwork, sewer, storm, water, retaining wall, asphalt, concrete, electrical, striping, signs

 

Location: puyallup, wa
Start/finish Date: june 2018 - september 2018
Contract: $576,022.08
Description: Project provides for the construction of a new culvert, creek channel, and habitat features.

 

Location: WSP Training Facility Shelton, Wa
Start/finish Date: May 2018 - october 2018
Contract: $1,281,750
Description: Replaced a deteriorated asphalt skid pan with a 40,000SF polished concrete slab. Only a handful of skid pans this size existing in the entire US. This facility is booked 300+ days/year by agencies from Washington, Oregon, Idaho, Montana and Hawaii..

 

Location: puyallup, Wa
Start/finish Date: august 2018 - september 2018
Contract: $2,760,692.81
Description: Construction of engineered log matrix’s to stabilize the existing channel and banks.

 

Location: Tumwater, wa
Start/finish Date: august 2018 - october 2018
Contract: $1,536,818
Description: This project provides for, but is not limited to: The construction of approximately 1,640 linear feet of concrete traffic curb and gutter, 750 tons of HMA, Fiber Reinforced, 7,700 tons of Roadway Ex. and Embankment Compaction (measured per ton of CSBC), 950 square yards of planing, 599 linear feet of storm pipe, 700 square yard of concrete sidewalk, 3,000 square feet of Retaining Wall, 685 linear feet of sewer pipe, 830 linear feet of water main, illumination system, PSE Schedule 74 Overhead Conversion, traffic control, pavement markings.

 

Location: federal way, wa
Start/finish Date: october 2018-december 2018
Contract: $742,742
Description: Project provides for the construction of sidewalk, retaining wall, illumination, and compact roundabout improvements.

 

Location: Tumwater, wa
Start/finish Date: january 2019-october 2019
Contract: $3,343,100
Description: 79 lot residential housing plat complete including logging, clearing, erosion control, site grading, sewer, storm drainage, water, JUT trenching, streets, sidewalk, lighting along with site grading for 87 future phase building lots.

 

Location: : Intersection of State Route 510 and Meridian Road SE, WA
Start/finish Date: Jan 2019 – Nov 2019
Contract: $2,484,484.00
Description: Project provides for the construction of a roundabout at the intersection of SR 510 and Meridian Rd SE in Thurston County to reduce the frequency and severity of collisions and improve motorist safety. Additional work will consist of HMA inlay of the existing lanes on SR 510. Work activities include clearing and grubbing, roadway excavation and embankment, surfacing, pavement repair, drainage, hot mix asphalt and cement concrete paving, guardrail, signing and illumination, landscaping, pavement marking, and traffic control.