Location: lacey, wa
Start/finish Date: march 2020 - may 2021
Contract: $5,025,800
Description: 79 lot residential housing plat complete including logging, clearing, erosion control, site grading, retaining walls, sewer, storm drainage, water, JUT trenching, streets, sidewalks, lighting, frontage improvements along with site grading for 43 future phase building lots.

 

Location: kent, wa
Start/finish Date: june 2020 - present
Contract: $4,759,759
Description: Project provides for the construction of a two-lane roundabout at the intersection of 4th Avenue S and Willis Street (SR 516). The project also includes new storm drainage, illumination, decorative sidewalks and other streetscape amenities.

 

Location: tumwater, wa
Start/finish Date: july 2020 - april 2021
Contract: $3,894,894
Description: Project provides for resurfacing of City streets consisting of approximately 10,250 tons of hot mix asphalt, 26,000 square yards of chip seal, 2,200 tons of crushed surfacing, 54,000 square yards of planing bituminous pavement, 44,250 square yards of pavement reinforcement interlayer, 1,790 square yards of cement concrete sidewalk and curb ramps, traffic signal work, clean-up and other work.

 

Location: tumwater, wa
Start/finish Date: july 2020 - may 2021
Contract: $4,324,400
Description: 140 Lot residential housing plat complete including erosion control, site grading, retaining walls, sewer, storm drainage, water, JUT trenching, streets, sidewalks, lighting.

 

Location: tumwater, wa
Start/finish Date: october 2020 - january 2022
Contract: $2,594,594
Description: Project provides for sitework that includes the following: erosion control, demolition, clear / grub, excavation / embankment, retaining walls, storm drainage, sanitary sewer, water distribution, road / sidewalk improvements, site lighting, monuments, stripe / sign, and irrigation services.

 

Location: port angeles, wa
Start/finish Date: march 2020 - October 2022
Contract: $2,069,069
Description: 1.01 miles of US 101, MP 251.65 to MP 252.66; and 5.82 miles of US 101, MP 256.55 to MP 262.37 during daytime and nighttime work hours in Clallam County by performing roadway excavation, installing drainage structures and concrete storm sewer pipe, placing crushed surfacing base course, performing HMA paving, performing HMA pavement repair, installing curb and gutter, placing topsoil, planting, installing guardrail, installing recessed pavement markers, pavement markings, guideposts, paint line, plastic pavement markings, maintaining traffic control.